Industry experts weigh in on the Certificate of Completion and Compliance

Posted: 06 Jun 2013 05:17 AM PDT

DESPITE being in effect for the last six years, the Certificate of Completion and Compliance (CCC), which has replaced the Certificate of Fitness for Occupation (CF), is still a murky issue to many.

The biggest difference between the two is in the move towards self-regulation in the new system. Now the power to issue a CCC is with the professionals in charge of the project as opposed to the CF, which was issued by the local authority.

These professionals are the ones directly responsible for the project and are required to countersign on all 21 G Forms before the CCC can be issued.

Each form addresses a specific parts of the project including earthworks, foundation, internal water plumbing, fire safety, sewage, road and drains, street lighting and landscaping.

These forms are also signed by the contractors including the electrician or plumber and where necessary, attached with supporting documents issued by bodies such as Tenaga Nasional Bhd and the Fire and Rescue Department.

In a CCC, these professionals are called the Principal Submitting Person (PSP) and they can either be an architect, building draughtsman or engineer registered with their relevant professional regulatory bodies as governed by the Architects Act 1967 or Registration of Engineers Act 1967.

Is there real change?

One of the main reasons for the certification change is to cut red tape and delays, which is the bane of most property buyers.

But until today, such complaints remain common.

National House Buyers Association (HBA) honorary secretary-general Chang Kim Loong said many were unfamiliar with the new system.

"The most common complaint is that the implementation of the CCC varies from one local authority to another.

"In some cases, the local authority still need to 'approve' submitted forms before the PSP can issue the CCC. This contravenes the spirit of the new system," he said.

Chang added that there had been complaints of some local authorities wanting to conduct a physical inspection of the building before accepting the CCC.

This could cause a delay in the issuance of the CCC, resulting in public confusion, especially when buyers were told by the PSP that the local authorities had the last say.

Malaysian Institute of Architects (PAM) immediate past president Saifuddin Ahmad said there was no change on who was responsible in the new system.

"Even before the CCC came into place, the liability and responsibility lies with the PSP. This new system is merely a different way of doing things and involves more forms," he said.

He added that the CCC pushed PSPs to look into the inspection parts of projects and ultimately, it was better for the public to have a professional ensuring everything was done according to the law.

PAM has received complaints of PSPs signing the forms withoutinspection.

"If you have signed the forms, you are taking responsibility for it," he said, adding that the CCC forms were very specific and pinpoints the person responsible for each segment of the project.

According to the Real Estate and Housing Developers' Association of Malaysia president Datuk Seri Michael K.C Yam, the system allowed building owners to move in as quickly as possible without compromising their safety.

"There are many ways delay can occur including the local authorities imposing additional conditions at the time of CF application.

"In the CCC, once technical aspects are complied with and without apparent threat to health and safety issues, the certificate can be issued," he said.

Through CCC, Vacant Possession is issued together and this overcomes the common problem in the past whereby homebuyers would receive their house keys but cannot move in as the CF had not been issued.

"The introduction of the matrix of responsibility in the Form Gs also leads to the improvement of work quality," he added.

Taking responsibility

Saifuddin said the CCC had opened up a can of worms on what actually takes place in the construction industry.

"Whenever the Board of Architects, which regulate architects and building draughtsman, receives a complaint, the secretariat will get both sides of the story.

"Then a board member looks into the case and comes up with the recommended action that is brought to the inquiry committee," he said, adding that the process was according to the Architects Act.

In some cases, the problem was caused by agreements gone sour or PSPs who have not been paid properly, as such there was no straightforward solution.

The majority of complaints, however, were on shoddy workmanship, especially in housing projects.

"The PSP does not come into the picture unless he or she did not provide proper supervision. Matters involving the Sales and Purchase Agreement (S&P) is between the developer and purchaser," said Saifuddin.

He added that they had even blacklisted PSPs.

"We have to look into the impact their actions have on public health and safety. We also will consider whether it is a first-time offence," Saifuddin said, adding that once registered as a professional, the onus was on them to act professionally.

Chang concurred there would always be errant practitioners who would spoil an otherwise well-devised system.

Yam said with responsible owners, work quality and safety were priority and in the event of failure or flaws, action can be taken against responsible parties.

"In the capital for instance, Kuala Lumpur has taken steps to circumvent problems with the launch of the integrity pact where developers sign an MoU with City Hall to ensure all obligations in the Development Order is dutifully complied with," he said.

Role of the local authority

Despite the final say being in the hands of the PSP, the local authorities still play a vital role.

"The project is based on the plans and building approval given by the local authority. Any amendments are also needed to be approved by them," explained Saifuddin.

He added that there was nothing to stop the authorities from visiting the site and there were provisions for them to take action.

"In any profession there are black sheep and PSPs who do not do their work properly.

"This needs to be reported. But a small group should not tarnish the entire profession," he said.

Ampang Jaya Municipal Council Building and Architecture Department director Yazid Sarkom said when there was a deviation from the approved plans, a report to the Board would be made.

"Usually it is possible to tell after a visual inspection if any building has not been done according to the plan.

"It is the gross alterations such as adding an additional floor that becomes a safety issue," said Yazid.

He added that that cases reported in Ampang were usually small and did not involve large projects.

The way forward

When a PSP signs the Form G, they take responsibility for that portion of the project until their passing.

Saifuddin said there was a need to look into the liability of a PSP such as limiting the number of years they were being held responsible.

"In the course of time, many things could happen to affect the building including the weather.

"Sometimes when something happens, it may not necessarily be the PSP's fault," he said, adding that many were quick to blame the architect.

Saifuddin said the construction of a building was a team effort and it was important to look into each problem to determine the right cause and who was responsible.

"In big projects, buildings are done in phases. Some contracts have components of a building designed and built by the contractor. These are the details that the public are usually not aware of," he said.

He said Malaysia lacked enforcement in many aspects.

"Sometimes when incidents happen, the ugly truth comes out that the construction works have not been approved by the local authority and no PSP was appointed.

"This makes us wonder sometimes how sure are we that the signage we commonly see outside construction sites are genuine?" he queried.

By law, all construction work needed the approval of the local authority.

Saifuddin said when it came to renovations, many were done illegally and could pose a safety hazard.

Chang said the system could be improved with the inclusion of an independent third party such as project insurer or even an independent building commissioner.

"They have to be knowledgeable, experienced and backed by the law.

"The present system takes up too much time and there is still a lot of red tape and a possible long legal process while housebuyers suffer."

Any system can fail when there is bias, noted Saifuddin.

"It must be remembered that in the final analysis, the PSP is under the payroll of his employer," he explained.

Yam believed the CCC could be further refined and fine-tuned as the industry progressed.

"We can learn by observing best practices from developed countries. There may be a future need for the introduction of some form of audit of independent checkers to provide oversight or even take over the role of issuance of CCC in order to avoid conflict of interest," he said.

LED lights to brighten up KL

Posted: 06 Jun 2013 05:17 AM PDT

EFFORTS to beautify and change the ambience of Kuala Lumpur through the use of LED (light-emitting diodes) lights are under way.

Kuala Lumpur mayor Datuk Seri Ahmad Phesal Talib said the city needed to strengthen its role as a dynamic commercial and business centre.

"Efforts to beautify the city centre with attractive and iconic lighting and designs will attract local and foreign tourists as well as improve our ranking," he said at a Kuala Lumpur City Hall (DBKL) seminar on the Kuala Lumpur Lighting Master Plan.

Ahmad Phesal said the plan was in line with the vision to realise Kuala Lumpur as a city of international standard.

"Based on reports by the World Tourism Organisation, Kuala Lumpur is ranked the seventh most visited city in the world."

In the CNN World Survey of the 10 best shopping destinations, we are in fourth place.

Among others, the plan is aimed at reducing energy consumption and enhancing the city's image and character through LED. It will be implemented in four phases.

Light Cibles chairman and chief executive officer Tengku Datin Paduka Setia Zatashah Sultan Sharafuddin Idris Shah said among the main initiatives was to change the ambience of Masjid Jamek using exterior lighting.

"The light fixtures will be placed to accentuate the architectural features of outstanding buildings and structures, including Masjid Jamek.

"They will enhance the beauty of the buildings and promote the architectural wealth of the city," she said.

Ahmad Phesal said RM1mil had been allocated for the Masjid Jamek project as a showcase of the lighting master plan.

"DBKL is also committed to light up the 2km-stretch from the National Mosque to the Sogo building that includes Dataran Merdeka and Jalan Mahkamah.

"We hope to complete it by the end of this year.

"The plan is important not only in beautifying the city centre but also for security reasons.

All new developments in the city centre will need to adhere to the lighting master plans," he said. He added that RM5mil would also be allocated for repainting and lighting installations at heritage buildings.